Uvinza–Musongati Railway: Where Does Burundi’s Landmark Project Stand?

Share this post:

Burundi’s long-awaited Uvinza–Musongati railway project has moved from the planning stage into implementation, but major construction work on the 282-kilometer line is still awaiting key financing and preparatory steps.

The railway, being developed in partnership with Tanzania, is designed to strengthen regional connectivity and facilitate the movement of people and goods between Burundi, Tanzania and, ultimately, the Democratic Republic of Congo.

A major milestone came on August 15, 2025, when Burundi officially launched the Uvinza–Musongati railway project in Musongati, in what was then Rutana Province. President Évariste Ndayishimiye and Tanzanian Prime Minister Kassim Majaliwa attended the ceremony and laid the foundation stone. The two leaders also inspected the first 50 meters of railway track, marking the formal start of the project.

The 282-kilometer line is expected to include five stations in Tanzania and three in Burundi. Supporters of the project say it could significantly reduce transportation costs, create employment and expand opportunities for trade within East Africa and beyond.

But more than a year after the launch ceremony, the project remains in a preparatory phase on the Burundian side.

According to Ir. Aaron Niyungeko, the project coordinator on the Burundian side, the company responsible for the construction has already reached Rutana Province. Authorities have allocated land for workers’ accommodation and for storing construction materials and equipment.

The proposed accommodation site is located in Rongero zone, Rutana, and Niyungeko said the site has already been approved by the Council of Ministers.

Another important part of the preparation concerns the sourcing of ballast, the crushed stone used in railway construction to support the track and help it withstand the weight of heavy trains. The project is expected to require approximately 2 million cubic meters of ballast.

The first quarry site identified for this purpose is located on Murama Hill, covering approximately 86 hectares. According to Niyungeko, social and accommodation-related studies for the site have been completed and submitted to the institution responsible for reviewing them.

The project is now awaiting authorization from the African Development Bank (AfDB), which is expected to provide the financing needed for the next stage. Construction works are expected to move into a more substantive phase once the required financing and approvals are secured.

The railway forms part of the broader effort to strengthen the Central Corridor, linking landlocked countries in the region with Tanzania’s transport network and the Port of Dar es Salaam.

The Uvinza–Musongati section is expected to provide Burundi with a direct railway connection to Tanzania, potentially reducing the cost and time involved in transporting goods. For Burundi, the project is also seen as an important infrastructure investment for connecting producers and businesses to regional markets.

The project therefore stands at an important transition point: the official launch has taken place, preliminary studies and site preparations are progressing, and construction logistics are being organized. However, the full-scale construction of the railway remains dependent on the completion of financing and other implementation requirements.

Once completed, the railway is expected to become one of Burundi’s most significant transport infrastructure projects, providing a new link between the country and the wider East African railway network.